8 Min. Lesezeit

A porous aluminium casting leaks under pressure test. A motor winding without varnish between the wires vibrates, abrades and fails. A transformer core with moisture in its paper insulation breaks down under voltage. In each case the fix is to fill the voids with a liquid — sealant, varnish, oil — and in each case the liquid cannot get in while air is in the way. Vacuum impregnation removes the air first, lets the liquid in under vacuum, then uses atmospheric or applied pressure to drive it deep. Thailand's die-casting shops (automotive housings, compressor bodies), motor and transformer builders all run impregnation autoclaves, and the vacuum pump on them is sized by a clear sequence of steps.

1. The cycle: dry vacuum, wet vacuum, pressure

  1. Load the parts into the autoclave (a horizontal or vertical pressure vessel, 0.5–20 m³) in a basket.
  2. Dry vacuum. Evacuate the vessel with the parts dry to the process pressure and hold — this is where air leaves the pores and capillaries. Hold time 5–30 minutes; the pressure depends on the pore size (below).
  3. Flood the impregnant (sealant, varnish, oil) into the vessel from a storage tank under vacuum — the vacuum draws it in, so no pump is needed, and the liquid arrives degassed.
  4. Wet vacuum. Hold vacuum over the flooded parts for 5–20 minutes; the remaining air in the pores bubbles up through the liquid.
  5. Release and pressurise. Vent to atmosphere and often apply 2–6 bar of compressed air or nitrogen for 10–30 minutes. The pressure difference between the vessel and the (evacuated) pore drives the liquid in.
  6. Drain the impregnant back to its tank, spin or drip the excess off, wash the parts (castings) and cure (heat for sealants and varnishes).

The vacuum pump works in steps 2 and 4, sees the vessel's air plus whatever the impregnant gives off, and must reach the process pressure quickly enough that the cycle time — which sets the shop's throughput — is acceptable.

Why do castings need 1–5 mbar but windings only 50–100 mbar?

Because of the size of the voids being filled. Porosity in a die casting is micro-porosity: interconnected channels of 10–100 µm, sometimes finer. The air in such a channel is held by surface tension and the deeper the vacuum, the more completely it is removed and the more completely the sealant can replace it; residual air at 50 mbar would be compressed to 1/20 of its volume under 1 bar of pressure but would still occupy 5 % of the pore — a leak path. Casting sealant specifications therefore call for ≤ 5 mbar, often 1–2 mbar, and a leak-tight autoclave. A winding's voids are macroscopic: the spaces between wires, slot liners and laminations, tens to hundreds of microns across and all connected to the surface. Air leaves them readily at 50–100 mbar, and the varnish — which is viscous and often solvent-borne — fills them under pressure. Going deeper on a varnish does nothing for fill and starts to boil the varnish's solvent or monomer off into the pump.

2. Casting impregnation

Methacrylate sealants (anaerobic or heat-cure) are the standard. The pump duty:

  • Dry vacuum: a 1 m³ autoclave with a 0.4 m³ basket of castings (free volume ~0.8 m³) to 2 mbar in 5 minutes: S = (0.8 / 0.083 h) × ln(1,013/2) = 9.6 × 6.2 ≈ 60 m³/h — then the knee: 2 mbar is four times a single-stage pump's ultimate, so the last decade is slow. A two-stage pump keeps its speed to 2 mbar: a DV90 (90 m³/h, 5 × 10⁻³ mbar) does the 5 minutes with margin.
  • Wet vacuum: the sealant has a low vapour pressure (methacrylate monomers 1–5 mbar at 20 °C — right at the process pressure, so some monomer does evaporate) and emits monomer vapour that polymerises in warm pump oil. A cold trap or an activated carbon canister on the inlet, gas ballast open, and oil changes on 200–300 hours. Dry pumps are increasingly used for exactly this reason: a DSI150 with its hot rotors passes the monomer to an exhaust trap and has no oil to polymerise.
  • Where the autoclave is larger (3–5 m³ for engine blocks and compressor housings) or the cycle must be faster, a Roots booster on the two-stage pump — MB150 on a DV90 — takes the last two decades in a fraction of the time.

Leak-tightness of the autoclave is part of the pump sizing: an autoclave with a worn door seal leaking 1 m³/h of air cannot hold 2 mbar with a 90 m³/h pump (1 m³/h × 1,013 / 90 ≈ 11 mbar). A pressure rise test (< 2 mbar/min isolated) is the first thing to check when the sealant results fall off.

3. Winding impregnation (VPI)

Vacuum pressure impregnation of motor stators, generator coils and transformer windings uses epoxy or polyester resins, often solvent-free but with reactive diluents (styrene in polyesters, which has a vapour pressure of 6 mbar at 20 °C and a strong smell).

  • Dry vacuum: a 3 m³ VPI tank with a 1 m³ stator (free volume ~2.5 m³) to 50 mbar in 10 minutes: S = (2.5 / 0.167) × ln(1,013/50) = 15 × 3 ≈ 45 m³/h; plant practice is to size for a faster pull and a hold at 20–50 mbar, so 100–150 m³/h for this tank. A single-stage V140 (132 m³/h, 0.5 mbar) is the usual pump; its ultimate is far below the process pressure, so it runs on its plateau. For large tanks (10–20 m³ for traction motors and generator stators), a V630 or an MB300 + V140 set.
  • Wet vacuum: the resin at 50 mbar gives off styrene or diluent vapour; the resin itself must not be pulled below its own vapour pressure or it will foam and lose diluent (ruining the viscosity for the next batch — VPI resin tanks are expensive). The controller holds 20–50 mbar; the pump sees styrene-laden air. Carbon canister on the inlet, ballast open, oil change schedule. Winding shops that have moved to DRV dry vane pumps (90 mbar ultimate) for VPI find they cannot reach the 50 mbar spec; the dry answer is claw (CL300, 50 mbar) or screw (DSI150).
  • Pre-drying. Windings are often heated under vacuum before impregnation (80–120 °C at 1–10 mbar for hours) to drive moisture out of the insulation; this is a deeper, longer, wetter duty on the same pump — gas ballast and a condensate trap, or a two-stage pump if the drying spec is 1 mbar.

4. Transformer drying and oil filling

Power and distribution transformers are dried before oil filling to remove moisture from the cellulose insulation, and the oil is degassed and filled under vacuum so no air is trapped in the windings. The transformer tank itself is the vacuum vessel: 5–100 m³, a welded steel box with gasketed covers and bushings — and a leak rate to match.

  • Drying: 100–120 °C (hot-air or hot-oil spray) at < 1 mbar for 24–72 hours, the vapour load being the water in the paper — tens of kilograms. A Roots booster on a two-stage or dry screw backing pump with a large condenser (cold trap) between booster and backing pump: MB600 on a DV175 or DSI300 for a 20 m³ tank, the condenser catching the water so the backing pump's oil survives three days of it. Dew-point measurement on the gas leaving the tank is the end-point.
  • Oil filling: the tank is held at < 1–5 mbar while degassed oil is admitted from below. Same pump set. The oil arrives from a degassing plant — a separate vacuum unit covered in the companion note on transformer oil degassing and dehydration.

5. Managing the vapour

Across all three duties the pump's enemy is the impregnant's vapour:

Impregnant Vapour Effect on oil-sealed pump Protection
Methacrylate sealant Monomer, 1–5 mbar v.p. Polymerises in oil; vane sticking Cold trap or carbon; ballast; 200–300 h oil; or dry screw
Polyester VPI resin Styrene, 6 mbar v.p. Dissolves, raises ultimate, smell Carbon canister; ballast; hold ≥ 20 mbar
Epoxy VPI resin Reactive diluent, low v.p. Mild Ballast; cold trap on pre-dry
Transformer oil Water from paper; oil mist Water emulsifies oil Condenser / cold trap before backing pump; ballast

6. Worked lines

Duty Vessel Process pressure Dr.Vakuum answer
Die-casting porosity sealing, 1 m³ autoclave 0.8 m³ free 2 mbar in 5 min DV90 + cold trap
Compressor housings, 4 m³ autoclave 3 m³ free 1 mbar in 8 min MB150 + DV90, or DSI150
Motor VPI, 3 m³ tank 2.5 m³ free 50 mbar hold V140 + carbon canister
Generator stator VPI, 15 m³ tank, pre-dry at 1 mbar 12 m³ free 1 mbar pre-dry; 30 mbar VPI MB300 + V301, condensate trap
Transformer drying and filling, 20 m³ 15 m³ free < 1 mbar, 48 h MB600 + condenser + DSI300

Recommended Dr.Vakuum machines

Two-stage oil-sealed vane (DV Series) — casting impregnation at 1–5 mbar: DV60, DV90, DV175.

Single-stage oil-sealed vane (V Series) — winding VPI at 20–100 mbar: V140, V301, V630.

Dry screw (DSI Series) — monomer and styrene without oil: DSI150, DSI300.

Roots boosters (MB Series) — large autoclaves and transformer tanks: MB150, MB300, MB600.

Autoclave to pump. Tell us the vessel volume, the basket, the process pressure and the impregnant, and we will size the pump and the trap — and tell you the leak rate the vessel has to meet. Talk to an engineer.